Annexation Phase V – Project 10 – Arran Hills (west)

Project Details Downloads
Estimated Construction Start: April 2012 Project Map (PDF)
Completion: June 2013 Construction Schedule
Estimated Cost: $1,665,335
Served: 325
Engineer Design Firm: W.K. Dickson
Construction: Utilities Plus, Inc.
Search Installation by Street

Construction is complete.

On January 13, 2014, the Fayetteville City Council approved utility assessments for properties receiving benefit of the utility extension.  Assessments were mailed to the address on record with the Cumberland County tax office at the time of the assessment.   To review assessment information using your property’s Parcel Identification Number (PIN), please click  here or contact PWC’s Assessment Department at 910-223-4106 or 910-223-4254.