Annexation Phase V – Project 32 – East Section 1 – Wendover Place, Hickory Run, Pine Crest, Pine Ridge Acres

Project Details

  • Design Start: January 2018
  • Design Completion: December 2021
  • Construction Start: June 2022
  • Construction Complete: February 2024
  • Available for Connection:
  • Services:  Sewer - 126 | Water - 79
  • Engineer Design Firm: WK Dickson
  • Construction Contract: TA Loving

Installation Completed/Connections Available 

Utility improvements are now complete and available for connection for the properties in the Phase 5 Annexation Area 32 Ease Section 1 Project.

A licensed plumber will be needed in order to connect a property’s plumbing to the newly installed sewer. When selecting a plumber, it is recommended that to get more than one quote from plumbers to ensure that the quote is reasonable. The property owner assumes all costs associated with connecting to the sanitary sewer system and the individual plumbing expenses are paid directly to the plumber. The resident homeowner may perform the work yourself after securing a plumbing permit from the City of Fayetteville Inspections Department.

Once a property is connected to the sewer mains, call PWC at (910) 223-4600 to establish your sanitary sewer services and refer to the Phase 5 Annexation Area 32 East Section 1 Project.

This information is subject to change.